SHMPAC fully funded and work to start in November

Thursday 4, July 2019 | News |

The Sir Howard Morrison Performing Arts Centre project is now fully funded and work is set to start later this year.

A total of $22.5 million has been secured for the strengthening and refurbishment of the facility, ensuring the ability to create a fit-for-purpose centre which will enable Rotorua to showcase its rich and diverse performing arts and attract shows from elsewhere.

In addition to Rotorua Lakes Council’s contribution of $11.5million, the project team has secured an additional $11.0 million in external funding. “It’s all systems go,” Rotorua Mayor Steve Chadwick says.

“The project team has done a fantastic job to secure the external funding support needed, so this vision can now come to fruition for our community.”

Construction will get underway in November this year and is expected to take 12 – 18 months.

“There has been a huge amount of detailed planning, consultation and funding work to get us to this point,” Council’s Arts & Culture Manager Stewart Brown says. “The next few months will include completing the detailed construction drawings, getting the building consent and awarding the construction tender,” says Mr Brown. “With the funding target met, we’re now at a very exciting stage in the project. Once construction starts, the community will be able to see things progressing,” he says.

The approved design, led by architects Shand Shelton, will expose some of the original qualities of this category one heritage building, while introducing a contemporary feel to the interior through the use of warm wood. Spaces, facilities and services throughout the building will be optimised for performing arts.

Stories of Ngāti Whakaue and Te Arawa, and recognition of the legacy of Sir Howard Morrison, will be also be featured.

What has happened since the centre closed?

  •  3 November 2017: The Sir Howard Morrison Performing Arts Centre closed for earthquake strengthening
  • November 2017: Business plan completed outlining options for redeveloping the centre
  • January – July 2018: Architectural design competition resulted in Shand Shelton being appointed to lead the redesign of the building for performing arts
  • April 2018: Detailed seismic assessment rated the building at 25% of new building standard. Buildings below 34% are considered earthquake prone, while those under 67% are considered earthquake risk
  • August 2018: Resource consent approved based on concept designs
  • May 2019: Preliminary designs completed
  • June 2019: Fully funded

Next steps

  • Current status: Developed design underway
  • Detailed design complete: November 2019
  • Preconstruction enabling works: July – December 2019
  • Construction works: November 2019 –2021
  • Expected re-opening to the public: March 2021

Funding partners

  • Rotorua Lakes Council: $11.5 million
  • Lottery Grants Board: $5.2 million
  • Glenn Family Foundation: $3.0 million
  • Rotorua Trust: $1.5 million
  • NZCT: $1.0 million
  • Ngāti Whakaue Trusts: $150,000
  • One Foundation: $125,000
  • Total secured funding: $22.5 million

•3 November 2017: The Sir Howard Morrison Performing Arts Centre closed for earthquake strengthening •November 2017: Business plan completed outlining options for redeveloping the centre •January – July 2018: Architectural design competition resulted in Shand Shelton being appointed to lead the redesign of the building for performing arts •April 2018: Detailed seismic assessment rated the building at 25% of new building standard. Buildings below 34% are considered earthquake prone, while those under 67% are considered earthquake risk •August 2018: Resource consent approved based on concept designs •May 2019: Preliminary designs completed •June 2019: Fully funded Next steps Current status: Developed design underway Detailed design complete: November 2019 Preconstruction enabling works: July – December 2019 Construction works: November 2019 –2021 Expected re-opening to the public: March 2021 Funding partners Rotorua Lakes Council: $11.5 million Lottery Grants Board: $5.2 million Glenn Family Foundation: $3.0 million Rotorua Trust: $1.5 million NZCT: $1.0 million Ngāti Whakaue Trusts: $150,000 One Foundation: $125,000 Total secured funding: $22.5 million

Top